Written by Justin, Principal. 12 November 2026.
Just over half (50.8%) of applications to discharge planning conditions were decided inside the 8-week target, and the median took 70 days (Home Builders Federation, 23 October 2026).
You have the permission. The architect has framed the decision notice. And then someone reads condition 7, which says nothing may start until the drainage details are approved. Planning permission is the front door. Pre-commencement conditions are the second door, and the council holds that key too.
The 30-second version
- A pre-commencement condition must be discharged before work starts. No discharge, no day one.
- The trade body's research found the median decision took 70 days, against a target of 56 (8 weeks).
- It varied widely by council: some decided over 75% on time, others only 18%.
- If your facility ties the first drawdown to discharge, the council's clock is also your funder's clock.
What the study found
The Home Builders Federation (HBF), the trade body for housebuilders, ran Freedom of Information requests to planning authorities across England. Its release of 23 October 2026 reports:
| Measure | Result |
|---|---|
| Applications to discharge conditions decided within 8 weeks | 50.8% |
| Median decision time, 2025/26 | 70 days (25% over the target) |
| Top and bottom councils | Over 75% on time; as low as 18% |
| On-time decisions, 2023/24 then 2024/25 | 55.6% then 51.8% |
The HBF says these delays create unnecessary cost, uncertainty and risk for home builders. The HBF is a trade body, and the research was done with a lender partner. Read it as an informed view from one side of the table. The council figures themselves come from FOI returns.
The release does not say how many councils or applications were counted, so we do not either.
What 14 days does to a draw schedule
Seventy days against 56 is only 14 days. On its own it is a fortnight. The real damage comes from when you submit. Take an illustrative scheme. Permission comes through on Monday 4 January 2027, and two pre-commencement conditions stand between it and the first drawdown.
| When you submit | Decision at the 56-day target | Decision at the 70-day median |
|---|---|---|
| Straight away, Mon 4 January 2027 | Mon 1 March 2027 | Mon 15 March 2027 |
| Six weeks later, Mon 15 February 2027 ("once the funding is signed") | Mon 12 April 2027 | Mon 26 April 2027 |
Sit on the submission for six weeks and the median decision slides from 15 March to 26 April. Suppose holding the site costs £1,500 a week for insurance, security and your own team. That is our guess, so put in your own. Six weeks is £9,000 before a single brick, and the interest on any loan is on top. Run your own figures in the development appraisal calculator. We counted calendar days from the day of submission and left out any wait while the council validates the application.
So put a date in the diary. Submit as soon as permission lands, and plan on the median rather than the target.
Before you commit to a start date
- Find out which conditions must be cleared before you start. Some can wait until later in the build.
- Read your term sheet for the first drawdown. If it is tied to discharge, note which conditions it names.
- Ask local agents and your planning consultant how this council does. Councils run from 18% on time to over 75%.
- If the conditions came up at pre-application, use that wording, so the submission answers them first time.
- Keep a log of each submission date, reference and officer, and chase. Nobody hurries a file they have forgotten.
- Put a 14-day buffer for the median in the programme, and decide now what you would do on day 71.
None of this predicts what your council will do. The 70-day median is a national figure, not your council's.
Planning, conditions and funding
Conditions sit between permission and the first draw, and a funder's monitoring surveyor can ask about them. We have lenders that will go up to 70% LTGDV, for the right developer with the right track record. A clear conditions log is part of looking like one. See development finance for how we structure draws and today's development rates for the market. For the earlier stage, waiting for the decision itself, read our market update on planning delays.
Tell us the site, where each condition stands and the programme. Indicative terms within about 24 hours. Loans from £500,000.
Two quick questions
What is a pre-commencement condition?
It is a condition on your permission that the council must formally sign off before building can start. Common ones cover drainage details, a construction management plan or samples of materials. Building before discharge can put the permission at risk, so ask your planning consultant before you mobilise.
Does a late decision mean my funding falls away?
Not by itself. It depends on what your facility says about the first drawdown and any long-stop date. Read both before you sign, and raise any gap with us early, while day 71 is still just a number in your programme.
For business or investment purposes only - never secured on a home you or your family live in.
Source. Home Builders Federation, Half of local planning authorities failing to discharge planning conditions within the statutory timeframe (23 October 2026). Dates in the example worked out from the calendar.