Written by Justin, Principal. 3 November 2026.
The short answer. In England, planning gain is what the council asks you to provide or pay in return for planning permission. It comes in two forms: Section 106 planning obligations and the Community Infrastructure Levy (CIL). In an appraisal it is a cost line, and anyone funding the scheme sees it the day you share the numbers. Loans start at £500,000. We have lenders that will go up to 70% LTGDV, for the right developer with the right track record. Indicative terms within about 24 hours.
In our nine-house example below, the council has been paid £171,000 before the first home sells.
Section 106 is negotiated and CIL is a fixed charge
They are different tools, so find out which one your council uses.
| Section 106 obligation | Community Infrastructure Levy | |
|---|---|---|
| What it is | A legal agreement to reduce the impact of your scheme: money, affordable homes, land or works | A charge on new development, set in pounds per square metre |
| Who sets it | You and the council agree it, scheme by scheme | The council, in a charging schedule approved by its full council |
| Where it applies | Only where it is needed to make the scheme acceptable. It must also relate directly to the development, in scale and kind | Only where the council has published a charging schedule |
| Smaller schemes | Affordable housing can be sought only on major residential schemes | The guidance says it can be collected from any size of scheme |
| When it is due | At the points written into the agreement | From the start of work, on the terms the council sets |
| Room to negotiate | Yes. You need not agree one, but refusing may mean refusal. It can be changed later by agreement | GOV.UK calls it a fixed charge. Relief is available only in set cases |
| If it goes wrong | After 5 years you can ask the council to change it, then appeal within 6 months of a refusal | Ask for a review within 28 days of the liability notice. A valuation appeal goes to the Valuation Office Agency within 60 days |
A Section 106 obligation runs with the land, so whoever owns the site next is bound by it. A CIL bill falls first on the landowner unless someone else takes on the liability.
Relief from CIL exists for social housing and charities, and for self-build homes. A council may also offer exceptional circumstances relief. That needs a published notice and a Section 106 agreement. The council must also judge that full payment would harm viability unacceptably. Claim any relief before work starts. (Sources 1 to 4.)
Nine houses, £171,000 of planning gain
An illustration, not a real client. A company builds nine houses of 100 square metres each, and sells them at £350,000. Every figure below is an assumption, and so are the council's terms. These are not any council's rates.
| The appraisal | Amount |
|---|---|
| Nine houses at £350,000 (GDV) | £3,150,000 |
| Land | £800,000 |
| Build, 900 sq m at £1,700 | £1,530,000 |
| CIL, 900 sq m at an assumed £120 a square metre | £108,000 |
| Section 106, assumed £7,000 a house | £63,000 |
| Fees, utilities and contingency | £230,000 |
| Total cost | £2,731,000 |
| Left before finance and sales costs | £419,000, 13.3% of GDV |
Take the planning gain out and the same scheme costs £2,560,000 and leaves £590,000, or 18.7% of GDV. So £171,000 of planning gain takes 29% of the margin the scheme would otherwise have. That is why it belongs in the appraisal before you agree the land price, not after.
Say the loan is £1,900,000, which is 60.3% of GDV and 69.6% of cost. The company puts in the other £831,000.
Both bills arrive before the first sale
Cash for planning gain goes out early. GOV.UK puts it simply: few if any developments generate value until they are complete. Here is the same scheme with assumed dates.
| When | What falls due | Running total paid |
|---|---|---|
| Month 1 | Section 106, first half on start of work: £31,500 | £31,500 |
| Month 3 | CIL, in full about 60 days after the intended start: £108,000 | £139,500 |
| Month 11 | Section 106, second half before first occupation: £31,500 | £171,000 |
| Month 12 onward | Houses start to sell | £171,000 |
The dates are ours. When money falls due is a matter for each council, in two ways.
- CIL. Suppose someone has taken on liability and sent a commencement notice. If the council has no instalment policy, the whole sum is payable 60 days after the intended start (regulation 70). A council that publishes an instalment policy chooses the number, size and timing of payments. If nobody takes on liability, the bill falls to the landowner, who cannot use instalments. Miss the commencement notice and you may lose instalments too.
- Section 106. The agreement sets the triggers. For money paid in place of homes, the guidance suggests a completion certificate as one possible trigger. Other triggers are possible.
(Sources 1 to 3 and 5.)
Try your own sums in the development finance calculator, see today's development rates, and read our development finance guide for how the funding works.
Ask the council for these four things before you offer
- The draft heads of terms. GOV.UK says councils may add heads of terms for Section 106 agreements to their local list of application requirements. Ask what is on it, and for the council's model agreement, if it has one.
- The charging schedule and instalment policy. CIL applies only where a schedule is published. Check the date it took effect, the rate for your use, and whether payment by instalments is offered.
- The infrastructure funding statement. Councils that receive these payments must publish one each year. The guidance says the records should include trigger points and deadlines for contributions.
- The liability notice. Once the council has worked out the CIL, it serves this notice. Its payment procedure and your 28-day review window both start there.
(Sources 1, 2 and 5.)
Planning gain goes into the figures you send us
Planning gain changes the size of a cost line and when the cash goes out. When you send us a scheme, include the planning decision, the Section 106 heads of terms and the CIL estimate.
Affordable homes written into the agreement have their own page: Section 106 and affordable housing. Schemes under permitted development rights are covered in our permitted development finance guide.
Our view
Treat planning gain as a price you can read before you bid. The charging schedule is public, and you can ask the council for the Section 106 heads of terms. A developer who has both in hand before offering for the land is negotiating from numbers. A developer who waits for the decision notice is guessing. Put the full amount in the appraisal, then check that you can still pay it before the first house is sold.
Three things developers ask
Can one scheme owe both Section 106 and CIL?
Yes. GOV.UK says councils can spend money from both on the same piece of infrastructure. Your appraisal needs both lines.
Who pays CIL if I buy a site that already has permission?
The landowner is ultimately liable, but anyone involved can take on the liability. Agree this in the contract, and before work starts.
Can I get a lower bill on a scheme that barely stacks up?
Possibly, through exceptional circumstances relief, but only if the council has published a notice that it offers it. The scheme also needs a Section 106 agreement.
Pricing a site with Section 106 and CIL on it? Send us the planning decision, the costs and the loan you want.
For business or investment purposes only - never secured on a home you or your family live in.
Sources. (1) GOV.UK, Planning Practice Guidance, "Planning obligations", last updated 1 September 2019, read 3 November 2026. (2) GOV.UK, Planning Practice Guidance, "Community Infrastructure Levy", last updated 17 June 2026, read 3 November 2026. (3) The Community Infrastructure Levy Regulations 2010, regulations 70 and 122, legislation.gov.uk, latest available (revised) version, read 3 November 2026. (4) Town and Country Planning Act 1990, section 106, legislation.gov.uk, up to date to 2 November 2026, read 3 November 2026. (5) Sources 1 and 2, the sections on payment and instalments, infrastructure funding statements and local lists.