Refurbishment Development Finance: When the Building Is the Risk

2 November 2026 · 7 min read

Written by Justin, Principal. Last updated 2 November 2026.

Some 4.0 million homes in England failed the Decent Homes Standard in 2024. Each of them needs somebody to refurbish it, and whoever does will pay the invoices long before the sale completes.

The short answer. Structural work, rewiring, a new roof, damp and the rest, on a building that is not fit to let or sell as it stands: that is the heavy refurbishment we arrange development finance for. Loans start at £500,000. We have lenders that will go up to 70% LTGDV, for the right developer with the right track record. Indicative terms within about 24 hours.

Old Stock, Newer Rules

The English Housing Survey is the government's yearly look inside the country's homes. Three of its numbers explain why heavy refurbishment is a steady line of work.

The first is age. In 2024 England had an estimated 25.6 million homes, and the oldest of them sit with landlords. Pre-1919 homes make up 32% of the privately rented stock. For owner-occupied homes the share is 20%, and for social rented homes 6%. (Source 1.)

The second is condition. The survey came out on 29 January 2026. It found 4.0 million homes, or 15%, failing the current Decent Homes Standard. It also counted 2.3 million (9%) with a Category 1 hazard and 1.4 million (5%) with a damp problem. (Source 2.)

The third is a deadline. On 21 January 2026 the government said private landlords in England and Wales would have to bring their homes up to EPC C by 1 October 2030. The government plans a cap of £10,000 a property on landlord spend, and its own impact assessment puts the average at £5,400. It also says the changes need Parliament's approval and aims to bring them into force in 2027. That is a plan with a date on it, not a law yet, so treat it as a watch item. (Source 3.)

None of that makes your scheme good. It does mean that a worn-out building bought at the right price is a recognisable kind of job, and that energy work is no longer an afterthought for anything you plan to let.

One tax point while you cost it. HMRC's manual says reduced-rate VAT on renovating empty residential property depends on a two-year empty rule and, where needed, a valid certificate. Ask your accountant before the work starts, not after. (Source 4.)

Where Light Ends and Heavy Begins

Kitchens, floors, paint: that is light refurbishment, the cosmetic end. Heavy refurbishment gets into the structure, the services or both, and while it is going on the building may be uninhabitable. The lender's view follows the work. Light work is a quick bridging job. Heavy work is a build programme, with a budget, stages and someone independent checking each one. That someone is the monitoring surveyor.

What the work is Typical finance What the lender watches
Cosmetic, building habitable A bridging loan, often a single advance The value after works and your exit
Structural or services, building not habitable A staged development facility The budget, the contingency, each stage signed off
Change of use or conversion Development finance, with the planning route as the key risk See our conversion guide

If your project is on the first row, our bridging site is the better start. This page is about the second row.

A Tired Block, Six Flats, Six Draws

This is an illustrative scheme, not a real client or a forecast. The sale prices are assumptions.

A developer pays £480,000 for six run-down flats in one pre-1919 block. Leaking roof, damp ground floor, wiring older than she is, heating in name only. Her plan is a full refurbishment, with each flat assumed to sell for £190,000. Six of those make a gross development value (GDV) of £1,140,000.

Line Amount
Purchase £480,000
Works: roof, structure, damp, rewire, heating, finishes £360,000
Professional fees £40,000
Contingency (about 14% of works) £50,000
Total cost £930,000
GDV £1,140,000
Margin before finance and sales costs £210,000

The loan she wants is £740,000, roughly 65% of GDV and 80% of cost. Her own £190,000 goes in before a penny of it. After that the money comes in stages, and each stage is released once the monitoring surveyor has visited and certified the work.

Draw Stage Amount
Draw 1 Completion: balance of the purchase £290,000
Draw 2 Roof, structure and damp £130,000
Draw 3 Rewire, plumbing and heating, first fix £100,000
Draw 4 Second fix and finishes £80,000
Draw 5 Completion, snagging and energy certificate £50,000
Draw 6 Professional fees and contingency £90,000
Total Total loan £740,000

The roof and the damp come first on purpose. Nothing else in the building survives a wet frame, and the surveyor will want to see them done before money moves on to plaster.

What if the building fights back?

Old buildings do. Suppose the works cost 20% more than planned.

Line Amount
Planned works £360,000
Overrun at 20% £72,000
Contingency held £50,000
Left for her to fund herself £22,000
Margin before finance and sales costs £188,000 (was £210,000)

She survives it, because the contingency was in the budget from day one and the margin was wide enough to take the rest. A scheme with a 4% margin and no contingency would not. A lender puts that question to every heavy refurbishment, and you are better off putting it to yourself first. Then test the programme the same way, because every month the works overrun is a month of interest with nothing to sell.

Cost of the facility Amount
Our fee: 1% of the gross loan, generally due on completion. On a complex case an application fee can apply, agreed in writing first £7,400
Lender's arrangement fee (lender fees typically 1% to 2%; 1% shown) £7,400
Valuation £3,000 to £15,000 or more, depending on deal size
Legal fees £5,000 to £25,000 or more, depending on deal size
Monitoring surveyor Generally £500 to £2,000, depending on the scheme
Interest Rolled up and repaid at exit at the rate in your term sheet; see today's development rates

Illustrative: every case is priced individually. Indicative terms are a guide, not an offer.

The exit is the sale of six flats, or a refinance of the finished block if she would rather let them. If she plans to let, EPC C is where she wants to land anyway.

Before You Ask

  • A schedule of works, costed, with the contingency shown as its own line.
  • Recent sold prices for finished flats near the site, because a lender prices the end result, not the dream.
  • Who is doing the work, and whether they have done this before.
  • The condition evidence: a survey, and photographs of the worst of it.
  • Your own track record, in a paragraph. We have lenders that will go up to 70% LTGDV, for the right developer with the right track record.

Two Stages, and When to Call

Development finance comes in two stages. Indicative terms arrive in about 24 hours. The lender's credit committee then considers the deal properly, and credit-backed terms typically follow from 5 working days, with the conditions and due diligence spelled out. Call us before you exchange on a building you have not had surveyed, so we can tell you whether the budget looks right to a lender.

Questions We Get on Refurbishment

Can I refurbish a building I cannot live in?

Yes. That is what heavy refurbishment finance is for. It is also why the lender wants a monitoring surveyor, who confirms the work done before each draw.

Does a rising EPC standard change the numbers?

If you will let the finished homes in England or Wales, build the work to reach EPC C before 1 October 2030, which is the deadline the government has named. Build the cost in now and treat the exact rules as a watch item until the law is passed.

What happens if the quote for the works comes in high?

You find out before you sign, which is the point of a costed schedule. If it still comes in high mid-build, the contingency takes the first hit and you fund the rest.

Got a refurbishment scheme? Send the building, the schedule of works, the costs and what you are asking for.

For business or investment purposes only - never secured on a home you or your family live in.

Sources. (1) GOV.UK, English Housing Survey 2024 to 2025, "Chapter 1: profile of households and dwellings", updated 9 July 2026. (2) GOV.UK, English Housing Survey 2024 to 2025 headline findings on housing quality and energy efficiency, "Introduction and key findings", published 29 January 2026. (3) GOV.UK, "Improving the energy performance of privately rented homes: government response", updated 21 January 2026. (4) GOV.UK, HMRC VAT Construction Manual VCONST07200, updated 4 August 2026.