Written by Justin, Principal. 16 November 2026.
Fabricated structural steel is 19.9% dearer than a year ago, in the 12 months to September 2026. Materials as a whole are up 7.2%. Those are the government's figures, published on 4 November.
If your cost plan was priced a year ago, the structural steel line may have grown faster than everything around it. Your quantity surveyor probably knows. Your contingency line may not have been told.
The 30-second version
- The government's building materials statistics (October 2026 edition, figures to September) have the All Work index up 7.2% on a year.
- Fabricated structural steel is up 19.9%, well clear of that. Rigid pipes and fittings are up 16.9%, which matters if your mechanical package is a big one. Reinforcing bar is up 16.1%, and because it goes into foundations, slabs and frame, it can hit more than one package.
- Some materials went the other way. Ready-mixed concrete is down 0.5% and imported sawn or planed wood is down 1.9%. The big rises are in steel products. Concrete and timber barely moved.
- A rise on one package can eat a contingency line almost whole, and who carries it depends on your contract.
- We would price the big packages again before you apply, not after the questions arrive.
Contingency or fixed price: who pays when structural steel moves?
Say your build costs £8m. Steel frame, £2m of it. You set aside £400,000 for contingency, 5% of the build in this example. Now put the whole 19.9% on the frame. That's rough, because a frame package can include labour and fixings as well as steel, but it's the worst case.
| Cost-plan line, price not fixed | Fixed-price contract signed before the rise | |
|---|---|---|
| Frame package as planned | £2,000,000 | £2,000,000 |
| Structural steel rise at 19.9% | +£398,000 | £0 to you (the contractor's risk) |
| Contingency available | £400,000 | £400,000 |
| Contingency left after steel | £2,000 (almost nothing) | £400,000 untouched |
| Draw schedule effect | Contingency almost fully drawn, any other overrun needs extra equity | Draws follow the contract sum, £8,000,000 |
Illustrative: every case is priced individually, and nothing here is a rate.
The left column is the uncomfortable one. A 5% contingency was meant for surprises across the whole job. Here one package uses 99.5% of it, which leaves £2,000 for the groundworks, the weather or the planning condition nobody expected.
The right column looks better, and often is. But a fixed price is fixed at the date it was agreed. Tender today and the contractor will usually have put today's steel price inside it. Either way the increase lands somewhere: in your cost plan, or in the number the contractor asks for.
What to have clear in your draw schedule
A monitoring surveyor (a third-party cost, generally £500 to £2,000) checks work done against money drawn. Be ready to answer three questions:
- is the contingency a separate line, or hidden inside the packages?
- is each large package fixed price, provisional sum or still an estimate?
- after each draw, what's left in the pot, and where did the rest go?
A provisional sum holds a place in the budget until a price exists. That is fine early on. It is less comfortable on the package that just rose 19.9%.
Questions to take to your QS this week
- Which packages are fixed price, and as at what date?
- Work out what is left of the contingency if structural steel moved by the full 19.9%.
- Can the price move under the contract? If so, who gets to say so?
- Would a different programme or frame type change the answer?
- How much equity could you add if the contingency ran out?
What we can do
We arrange development finance for developers who have done their sums, and a re-priced cost plan is a good start. We have lenders that will go up to 70% LTGDV, for the right developer with the right track record. Indicative terms within about 24 hours. Loans from £500,000. Run your own numbers in the development appraisal calculator, see development finance, read our ground-up development finance guide or check current rates.
Talk to us on 0330 223 7873.
For business or investment purposes only - never secured on a home you or your family live in.
FAQs
Does a 19.9% structural steel rise mean my whole build cost is up 19.9%?
No. It applies to fabricated structural steel only. The wider All Work index rose 7.2%, and some materials fell. How much reaches your total depends on how much of the job is steel.
Does a fixed-price contract make the problem disappear?
It moves the risk to the contractor for the agreed scope, from the date of the agreement. A price agreed today already includes today's steel. Ask what the contract says about variations, and on what date its steel price was set.