Market Update

Structural steel up 20% in a year

16 November 2026 · 4 min read

Written by Justin, Principal. 16 November 2026.

Fabricated structural steel is 19.9% dearer than a year ago, in the 12 months to September 2026. Materials as a whole are up 7.2%. Those are the government's figures, published on 4 November.

If your cost plan was priced a year ago, the structural steel line may have grown faster than everything around it. Your quantity surveyor probably knows. Your contingency line may not have been told.

The 30-second version

  • The government's building materials statistics (October 2026 edition, figures to September) have the All Work index up 7.2% on a year.
  • Fabricated structural steel is up 19.9%, well clear of that. Rigid pipes and fittings are up 16.9%, which matters if your mechanical package is a big one. Reinforcing bar is up 16.1%, and because it goes into foundations, slabs and frame, it can hit more than one package.
  • Some materials went the other way. Ready-mixed concrete is down 0.5% and imported sawn or planed wood is down 1.9%. The big rises are in steel products. Concrete and timber barely moved.
  • A rise on one package can eat a contingency line almost whole, and who carries it depends on your contract.
  • We would price the big packages again before you apply, not after the questions arrive.

Contingency or fixed price: who pays when structural steel moves?

Say your build costs £8m. Steel frame, £2m of it. You set aside £400,000 for contingency, 5% of the build in this example. Now put the whole 19.9% on the frame. That's rough, because a frame package can include labour and fixings as well as steel, but it's the worst case.

Cost-plan line, price not fixed Fixed-price contract signed before the rise
Frame package as planned £2,000,000 £2,000,000
Structural steel rise at 19.9% +£398,000 £0 to you (the contractor's risk)
Contingency available £400,000 £400,000
Contingency left after steel £2,000 (almost nothing) £400,000 untouched
Draw schedule effect Contingency almost fully drawn, any other overrun needs extra equity Draws follow the contract sum, £8,000,000

Illustrative: every case is priced individually, and nothing here is a rate.

The left column is the uncomfortable one. A 5% contingency was meant for surprises across the whole job. Here one package uses 99.5% of it, which leaves £2,000 for the groundworks, the weather or the planning condition nobody expected.

The right column looks better, and often is. But a fixed price is fixed at the date it was agreed. Tender today and the contractor will usually have put today's steel price inside it. Either way the increase lands somewhere: in your cost plan, or in the number the contractor asks for.

What to have clear in your draw schedule

A monitoring surveyor (a third-party cost, generally £500 to £2,000) checks work done against money drawn. Be ready to answer three questions:

  • is the contingency a separate line, or hidden inside the packages?
  • is each large package fixed price, provisional sum or still an estimate?
  • after each draw, what's left in the pot, and where did the rest go?

A provisional sum holds a place in the budget until a price exists. That is fine early on. It is less comfortable on the package that just rose 19.9%.

Questions to take to your QS this week

  1. Which packages are fixed price, and as at what date?
  2. Work out what is left of the contingency if structural steel moved by the full 19.9%.
  3. Can the price move under the contract? If so, who gets to say so?
  4. Would a different programme or frame type change the answer?
  5. How much equity could you add if the contingency ran out?

What we can do

We arrange development finance for developers who have done their sums, and a re-priced cost plan is a good start. We have lenders that will go up to 70% LTGDV, for the right developer with the right track record. Indicative terms within about 24 hours. Loans from £500,000. Run your own numbers in the development appraisal calculator, see development finance, read our ground-up development finance guide or check current rates.

Talk to us on 0330 223 7873.

For business or investment purposes only - never secured on a home you or your family live in.

FAQs

Does a 19.9% structural steel rise mean my whole build cost is up 19.9%?

No. It applies to fabricated structural steel only. The wider All Work index rose 7.2%, and some materials fell. How much reaches your total depends on how much of the job is steel.

Does a fixed-price contract make the problem disappear?

It moves the risk to the contractor for the agreed scope, from the date of the agreement. A price agreed today already includes today's steel. Ask what the contract says about variations, and on what date its steel price was set.

Source: gov.uk, Department for Business, Innovation, Science and Trade, Building materials and components statistics, October 2026 edition (commentary, published 4 November 2026; reference month September 2026).